RAID Log Template (Risks, Assumptions, Issues, and Dependencies)

A single log to track a project's risks, assumptions, issues, and dependencies every week, each with an owner, a date, and an action.

Version of November 7, 2026

How to use this template

A RAID log brings together everything that could derail a project. Review it weekly with the team and take it to the steering committee when something crosses the escalation threshold. Every item needs a named owner and a dated next action: without them, it’s just a list of worries.

Definitions

  • Risk: something that could happen and would affect the project. Managed before it occurs.
  • Assumption: something we take as true without having confirmed it. If it turns out false, it becomes an issue.
  • Issue: something already happening that affects the project. Resolved or escalated.
  • Dependency: something the project needs from another team, project, or vendor to move forward.

Risk rating scale

Level Probability Impact
1 Unlikely (< 20%) Minor: absorbed within the plan
2 Possible (20–60%) Moderate: affects a milestone or part of budget
3 Likely (> 60%) High: affects the end date, cost, or scope

Priority = probability × impact. From 6 to 9: reviewed in every meeting and reported to the steering committee.

Log

ID Type Description Prob. Imp. Priority Owner Action or response Date Status
R1 Risk [Vendor X could delay the integration] 2 3 6 [name] [Request a weekly work plan] [date] Open
A1 Assumption [Key users will have 20% of their time] – – – [name] [Confirm with their managers] [date] To validate
I1 Issue [Test environment unavailable] – 3 – [name] [Escalate to infrastructure] [date] In progress
D1 Dependency [Data migration from project Y] – – – [name] [Agree on a delivery date] [date] Open

Good practices

  1. A well-written risk has a cause and an effect: “Because of [cause], [event] could happen, which would lead to [effect].”
  2. Close what no longer applies. Nobody reads a log with a hundred open items.
  3. Review assumptions at the start of each phase. They’re the most common source of surprises.
  4. Dependencies have two owners: the one who needs it and the one who delivers it.